For Mining and Drilling Clients.
Learn how to discover insights, workflows and navigate the DSR pages:
Overview Page
This page shows all the daily shift reports.
Mining clients can only view and export reports once they have been Validated by the contractor.
- The "Shift Info" holds 3 icons to hover over which indicate:
Expected Shifts Indicates if there are mismatched number of submitted shifts with Expected Shifts, either missing or extra.
Important: DSRs will not be sent for Approval to the mining client until all shifts for that day have been Validated and the Expected Shifts = Validated Shifts.Validations Indicates if there is something that needs further investigation in regards to a shift Attachments Indicates if a form or document has been attached to a shift - Search Bar: type any character to filter the contents of columns in the grid:
- Filters: click the filter icon
in a column header to apply a filter. Click inside the white box to reveal a dropdown of items you can select to filter on. You can see all columns that have a filter applied by noticing the purple filter icon
. To clear all filters including anything in the Search bar, click "Clear All Filters"
to the right of Search bar above the table, or for an individual filter, click the "x" or "Clear" within the input field in the filter window:
- Links: click on a link indicated by underlined purple text to be directed to that data item page. You can link to a Contract or Project.
- Status Indicators:
|
New | Drilling | ||
![]() |
Pending Validation | Drilling/Mining | ||
![]() |
Pending Approval | Drilling/Mining | ||
![]() |
Validated | Mining - shift needs to be reviewed and Approved | ||
![]() |
Pending Validation | Seen at the report level that needs review of a shift for a Rejected shift(s) | ||
![]() |
Rejected | Seen on a shift that has been sent back to the Contractor for review and editing | ||
![]() |
Validated |
Drilling - when No Approval Required |
||
![]() |
Approved | Drilling/Mining |
- Bulk Export: for exporting multiple reports. Each Contract will be exported separately into different zip files. Select all reports in the selection column, either individually, or checkbox in the column header which will select all that are filtered then click
.
You may also export an individual report with the icon in the last column.
- Resizable Columns: to resize columns, hover over the column edge until the arrow appears on your cursor, then click and drag.
To see a report and associated shifts, click anywhere in a row to navigate to the DSR Summary Page.
Summary Page
Validate/Approve all shifts here or click on a shift card for more details for the shift.
Note: A DSR will not be sent for Approval until all of the shifts for that report date have been Validated and the Expected shifts = the Validated shifts.
The Summary Page has the following sections:
-
- Identification Header
- Shifts Section
- Metrics: shows Total metrics for all shifts on this report date:
- Total Man Hours, Total Activity Hours, Total Distance Drilled, and Total Charges
- Visualizations: view breakdowns of each shift for Charges and Activities
- Identification Header:
- Report Date and Drill
- Report Status: reflects the number of reports and action needed
- Contract
- Project
- Client/Contractor
- Holes linked to the report and a survey icon
if there is any associated survey data on a hole. Clicking on a hole will take you to the Hole Page in a new tab
- Shifts Section:
See a shift card for each shift attached to this report showing high-level info and associated actions. Icons for Validationsand Documents
will appear if they exist for this report.
Update "Expected Shifts", or Downloadreports is also available.
Click anywhere on a card to go to the Shift Detail page for the shift. Alternatively, you can click on the arrowto expand/collapse the card:
In the expanded card, you can view the summary of data attached to this shift in the “Quick Links” which shows the number of items in each category. Clicking on a Quick Link will take you directly to the associated table on the Shift Detail Page:
You can also take action on each individual shift in the expanded card, or take action on All shifts at the bottom of the section:
To navigate to the next report for the same Drill, Contract and Project, you can use the Previous & Next DSR:
- Metrics: Totals for all shifts are shown here as well as any Attachments or Comments attached to a shift which you can hover over or click on to view when the icon is active:
To view details of Distance Drilled and Total Charges, click the dropdown arrow to expand:- Total Distance Drilled:
- Total Charges:
- Total Distance Drilled:
- Visualizations:
- Activities Breakdown per shift indicating both Billable and Non-Billable (shown with hatch marks). Hover over the bar to reveal details:
- Total Charges Breakdown per shift
- Activities Breakdown per shift indicating both Billable and Non-Billable (shown with hatch marks). Hover over the bar to reveal details:
Shift Detail Page
You can quickly navigate between the Overview, Summary and Detail pages by clicking on an item here:
You can navigate the detail page in 2 ways: by scrolling or alternatively by clicking on the icons of each category that remain at the top of the page on the left side of the header section. As well, the action buttons also remain available here to access from anywhere on the page:
There are 3 sections in the header for:
- Quick Links: click on a quick link to jump directly to a category table for more details. The “to Top ”
arrow will bring you back up to the top of the page. Navigate back to the Summary page with “back to Summary” button or in the Navigation Breadcrumbs above:
- Shift Info: to Edit or Delete and see Status:
- Navigation & Action section:
- Access the Previous/Next report for the same Drill/Contract/Project
- Navigate the shifts on this report by clicking on the shift color boxes
. The purple outlines indicate which shift you are viewing
- Take action on the report for the shift with Validate/Approve and have the option to navigate immediately to the next shift with the action "& Next" button.
On the Detail page you can see metrics for the shift selected (click to see dropdowns with more details for Distance Drilled, Charges and Drill Rates), and if there are any Comments or Attachments they will appear here which you can preview or download:
Below the metrics, view tables for each category:
Validations | ||
Workers | ||
![]() |
Activities | |
![]() |
Equipment | |
![]() |
Consumables | |
![]() |
Fluids | |
![]() |
Additional Charges | |
![]() |
Submitted Forms |
Actions for Shift Reports
![]() |
As a Contractor, prior to validation you can Edit or Delete a shift or record in a table | |
|
As a Contractor, for a New or Rejected shift, you can review and edit the shift and Validate, or Validate All shifts with the button below the shift cards | |
|
|
As a Contractor, to help speed up your validation process and navigation through reports, with one click you can validate a shift and go to the next shift of a report. Note: if you are on the last shift of a report then you will be taken to the first shift of the next report date |
|
|
As a Contractor, if a shift has been Validated but not yet Approved by the client, you may Re-Open the shift to make edits |
|
|
As a Contractor, you can delete All shifts at once with the button below the shift cards |
|
|
As a Mining Client, you can review and Approve a shift once it has been validated by the Contractor. You can Approve All shifts with the button below the shift cards |
![]() |
|
As a Mining Client, to help speed up your approval process and navigation through reports, with one click you can Approve a shift and go to the next shift of a report. Note: if you are on the last shift of a report then you will be taken to the first shift of the next report date |
![]() |
|
As a Mining Client, once a shift has been validated or approved, you can Reject the shift and add a note to return to the contractor. You can Reject All with the button below the shift cards |
Note: Editing a record will update all previous records where the items was selected. Deleting will archive the record item. It will not delete any previous record where the item was selected.
To add a new record for each section:
![]() |
Workers | |
![]() |
Activities | |
![]() |
Equipment | |
![]() |
Consumables | |
![]() |
Fluids | |
![]() |
Additional Charges |
Within the Activities section, the following items can be added to the relevant Activity:
![]() |
All Activities: Add Activity Worker | |
![]() |
All Activities: Add All Workers | |
![]() |
All Activities: Add Activity Equipment | |
![]() |
For Survey Activity: Add Survey Points | |
![]() |
For Cementing Activity: Add Plug Depths | |
![]() |
For Coring Activity: Add Core data | |
![]() |
|
For Directional Drilling Activity: Add Runs. Note: This is for Directional Drill Types only |
![]() |
|
For Samples: Add Sample data |
Drilling Activities: To learn more, click the links below for details:
Shift Detail Tables:
- Validations: potential issues flagged that may require attention when editing the report
- Workers: shows all workers that worked on that drill for the shift with both their Payroll and Man Hours
- Payroll Hours: calculated from the Start/End times of the worker’s shift
- Man Hours: calculated from the sum of the man hours recorded for that worker on each activity in the shift
- Activities: shows a chronological list of all activities entered for the shift, ordered by Time. You can re-sequence activities by clicking and dragging the Move arrow
on the top right of the table in the event they need to be re-ordered. The associated hole link listed at the top of the table will open the hole page in a new tab. View any Comments related to the activity underneath the table. Any additional activity-related data can be seen in the sub-tables when the expand icon
is clicked. You can see a count of sub-category items above each relevant table:
- Activity Workers
- Activity Equipment
- Surveys
- Cement Plugs
- Directional Drilling Runs. (Note: for details on Directional Runs please click here)
- Coring
- Equipment: shows all records entered onsite for the entire shift, not specific to an activity
- Consumables: shows all records entered for the shift
- Fluids: shows all records entered for the shift
- Samples: shows all samples if the Drill Type equals Reverse Circulation
- Additional Charges: any specific to a DSR shift (could be allocated to one specific hole or distributed to All holes). These can be positive or negative charges.
(Note: Additional Charges at the Management level are across all holes and are not specific to the shift.) - Submitted Documents: shows all submitted documents with the daily shift report. Click on the file name to preview the document or for the option to download.